Every time you switch something on, a power station or wind farm somewhere has to make a little more electricity in the same instant. Between the two sits one of the biggest machines in the country: the grid. This guide follows electricity from where it is made to your socket, explains why it changes voltage so many times on the way, and who looks after each part.
The journey in one picture
Why transmit at such high voltages?
Power is voltage times current. To move the same power you can use a high voltage and a small current, or a low voltage and a large current. The heat lost in a line is set by the current: it is I²R, so doubling the current gives four times the loss.
Moving 1,000 MW at 400 kV takes about 1,443 A. Moving the same power at 11 kV would take about 52,486 A. In the same conductors, the 11 kV line would lose about 1,322 times as much power as heat, because the current is 400 ÷ 11 ≈ 36 times larger and losses go with its square. That is why bulk power travels at the highest voltage, and why transformers, which only work on AC, made the AC grid possible.
Loss in a line = I² × R, and for the same power, I is proportional to 1 ÷ V
Generation
Large generators, whether driven by gas, steam from a nuclear reactor or water, make electricity at a generator voltage of up to about 25 kV. A generator transformer next to the station steps it up to transmission voltage. Big offshore wind farms collect power from their turbines on an array network, then step it up at an offshore substation and bring it ashore by cable.
A growing share of generation, such as solar farms, onshore wind and home solar panels, connects to the lower-voltage distribution network instead. This is called embedded or distributed generation. It means power can flow "backwards" up the network at times, which the network was not originally designed for, and is one reason DNOs now act more like system operators themselves.
Transmission
The transmission network in Great Britain runs at 400 kV and 275 kV, mostly on the large steel lattice towers you see across the countryside. In Scotland, 132 kV lines are also part of the transmission network; in England and Wales, 132 kV belongs to the distribution companies. The network is a single synchronous system running at 50 Hz, with undersea links (interconnectors) to Northern Ireland, Ireland and mainland Europe. Most interconnectors are HVDC, so the other systems don't have to be in step with ours.
Three companies own the transmission network: National Grid Electricity Transmission in England and Wales, SP Energy Networks (SP Transmission) in central and southern Scotland, and SSEN Transmission in the north of Scotland. Running the whole system, minute by minute, is the job of the National Energy System Operator (NESO), a public body that took over from National Grid ESO on 1 October 2024.
Grid supply points and distribution
Where the transmission network hands over to a distribution network is called a grid supply point (GSP). From there, a distribution network operator (DNO) steps the voltage down in stages:
| Voltage | What it does | Where you see it |
|---|---|---|
| 132 kV | Carries power across a region from the grid supply points | Smaller steel towers, or cables in cities |
| 33 kV | Feeds primary substations and large industrial customers | Wooden poles with three insulators, fenced substations |
| 11 kV | Feeds the distribution substations in streets and villages, and some factories | Wooden poles, cables under pavements, rings of substations |
| 400 V / 230 V | The low voltage (LV) mains that supply homes and businesses | Cables under the street, overhead lines in rural areas |
Some areas also use other voltages, such as 66 kV or 6.6 kV, for historical reasons. Great Britain has 14 distribution licence areas, based on the old area electricity boards, run by five company groups: UK Power Networks, National Grid Electricity Distribution, SP Energy Networks, SSEN (Scottish and Southern Electricity Networks) and Northern Powergrid. SP Energy Networks' owner, Iberdrola, bought Electricity North West in 2024, and it has traded as SP Electricity North West since August 2025. Your DNO is the company to call in a power cut, whichever supplier sends your bill. Dial 105, free, from anywhere in England, Scotland or Wales and you are put through to your local network operator.
The last step: your street
A distribution substation turns 11 kV into 400 V three-phase. Its low voltage side is a star with the neutral brought out and earthed, so each line is 230 V to neutral and 400 V to the other lines (see three-phase power explained). Houses are usually spread across the three phases to keep the load balanced, each with a single-phase 230 V service cable into a cut-out with the DNO's fuse.
The law sets what you should get. The Electricity Safety, Quality and Continuity Regulations 2002 (ESQCR) say a low voltage supply is declared at 230 V, with a permitted variation of 10% above to 6% below (about 216 V to 253 V), and the frequency at 50 Hz ± 1% (49.5 Hz to 50.5 Hz). Supplies at high voltage below 132 kV may vary by 6% either way.
How your installation is earthed depends on the DNO's network: most new homes get a TN-C-S (PME) supply, where the neutral and earth are combined in the supply cable; older cable networks give TN-S, and many rural overhead supplies are TT. Earthing systems explained covers what each means for your installation.
Keeping the frequency at 50 Hz
Electricity can't be stored on the wires, so generation has to match demand every second. The frequency tells NESO how well they match. If demand is higher than generation, the spinning generators slow down slightly and the frequency falls; if generation is higher, it rises. NESO normally keeps it between 49.8 Hz and 50.2 Hz by asking generators, batteries and large users to change their output within seconds.
If a large generator trips and the frequency falls far enough, automatic low frequency demand disconnection relays at substations switch off blocks of customers to save the rest of the system, starting at 48.8 Hz. On 9 August 2019 a lightning strike, followed by the near-simultaneous loss of two large generators, did exactly that: about 1.1 million customers were cut off for 15 to 20 minutes, and the rest of the grid stayed up.
Try it yourself
The network control room simulator puts you in charge of an 11 kV network: find a fault from the alarms, switch round it and get customers back on. The HV switching and LV switching simulators take you out on site.
Going deeper
Inertia and the rate of change of frequency
Large spinning generators store energy in their rotating mass. When a generator trips, that stored energy is released and slows how fast the frequency falls (the rate of change of frequency, RoCoF). Wind turbines, solar and batteries connect through power electronics and give no natural inertia, so as they replace conventional plant, NESO buys "stability" services from synchronous condensers and grid-forming inverters, and uses fast frequency response services from batteries that react in under a second.
Reactive power and voltage
Voltage on the transmission system is controlled mainly by reactive power. Long lightly loaded cables and lines generate reactive power and push voltage up, especially overnight; heavily loaded lines absorb it and voltage falls. Generators, shunt reactors, capacitor banks and static VAR compensators are adjusted to keep voltages within limits. On distribution networks, on-load tap changers at the primary substations keep the 11 kV busbar voltage near its target as load changes during the day.
Security of supply: N-1
The transmission system is planned so that losing any single circuit or generator (an "N-1" event) does not cut off customers or overload anything else. Distribution networks are planned to the ENA Engineering Recommendation P2 security of supply standard, which sets how quickly supply must be restored after a fault depending on the size of the demand group. That's why higher-voltage networks are built in rings and meshes, while a rural 11 kV spur or an LV feeder may have only one route.
Sources
The main references behind this guide. Numbers we worked out ourselves, such as the code outputs, come from running the code.
- The Electricity Safety, Quality and Continuity Regulations 2002, regulation 27: declared voltage and permitted variations
- Wikipedia: National Grid (Great Britain), transmission voltages, frequency limits and the 9 August 2019 disconnection (citing NESO / National Grid ESO reports)
- Wikipedia: Distribution network operator, the 14 GB licence areas (citing Ofgem); Electricity North West, Iberdrola ownership and the 2025 rename
- Wikipedia: National Energy System Operator, began operating 1 October 2024 (citing GOV.UK and Ofgem)
- Ofcom: a three-digit number (105) for the national power cut and electricity network safety service in England, Scotland and Wales