LV switching simulator
The switching and isolation procedures follow SSEN Distribution's Operational Safety Manual. If you switch for another DNO, your company's practice may differ in places.Follows SSEN’s LV procedures; other DNOs may differ. About this simulator
About this simulator and how it works
Switch a small low voltage network the way a UK distribution network operator does: phase out open points with the ladder method, backfeed to keep customers on, isolate link boxes, pillars, cabinets and overhead lines, prove dead with a voltage indicator (prove, test, prove), and deal with crossed phases, short circuits and open circuits.
How it works
You are an Authorised Person for LV switching. The network has two ground-mounted substations (Mill Lane, fed from Ashby Primary, and Station Road, fed from Brook Primary), a 100 kVA pole-mounted transformer at Pole 1 on the same HV feeder as Mill Lane, an overhead ABC line with a pole-termination fuse set at Pole 3 and an ABC link box at Pole 4, a street LV cabinet, a 4-way link box and two feeder pillars. Five normal open points join it all up.
- Level 1 covers single fuse operations with a Fusemate, phasing out an open point with the ladder, and moving an open point.
- Level 2 covers isolations for jointers, with backfeeds and restoration, and putting an overhead line onto the cable network while Control changes a pole transformer.
- Level 3 covers plant changes: a link box, an LV cabinet and a whole substation's load.
- Level 4 covers faults: crossed phases after a joint, a phase-to-phase short circuit, a broken phase conductor, and records that don't match the network.
Each job gives up to three stars: one for finishing with the network safe, one for no safety strikes or slips, and one for keeping customer minutes lost within par without opening the hints. Three strikes stop the job; closing a link onto a fault or bonding live conductors stops it at once.
The rules it checks
The procedures follow SSEN Distribution's published Operational Safety Manual. Where the public documents are silent, the simulator uses common practice and says so.
- Before and after every operation. Check the voltages on the way before you withdraw or insert a fuse or link and again afterwards (OSM-027 8.8, 9.1.8, 9.2.1). Fuses are checked for continuity before they go in (8.7.5, 9.3.3). Warn everyone before you make a circuit live (9.3.5).
- Phasing. Closing an open point with both sides live makes a parallel, so it is phased out first. The ladder method used here: prove the indicator, confirm each phase to neutral on both sides, then test every busbar phase against every cable phase. Like phases read nothing (or a few volts where the substations come from different HV sources); unlike phases read about 415 V. After cores have been rearranged, phasing is confirmed at the closest open point (OSM-066 17.2.2) and phase rotation is checked (OSM-027 9.2.3, 9.3.6).
- Parallels. Tell Control before paralleling substations, keep the parallel as short as practicable and tell Control when it is broken (OSM-027 9.1.4, 9.1.7). The LV fuses on a distribution transformer are the boundary with HV Control and are operated only on Control's instruction (OSM-027 8.2.2).
- Isolation. Points of isolation at every interconnectable end and every open point, each with a Caution Notice carrying your name, date and phone number (OSM-016 7.3, 7.4). No cable is connected or disconnected in a pillar, cabinet or link box with any part of it live, so plant changes are isolated at the far ends (OSM-066 14.1.1). Never assume the network matches the records: test (OSM-016 8.2).
- Proving dead. Prove the indicator on a proving unit, test each phase to neutral and to earth, neutral to earth, and between phases, then prove it again (OSM-027 9.5.4). Work is proved dead at the point of work (Operational Safety Rules 8.2.6). For a healthy cable isolated at both ends, one test at either end proves the whole section dead; a damaged or faulty cable must be proved dead at every point of isolation, because a broken core can be backfed (OSM-067 10.5). Any unexpected reading is investigated before work goes on (9.5.5). Conductors are proved dead before a bonding device is fitted (9.6.3); on LV, "Earthed" means the phases bonded to the neutral (4.2). Where customer generation could backfeed, conductors in a pillar or cabinet are bonded before work (OSM-066 14.1.4).
- Faults. Never replace a fuse onto a phase-to-phase fault (OSM-027 9.2.5). Where the condition of a circuit is unknown, or after a repair, re-energise with a Fusemate first (OSM-027 9.2.2, 9.2.4; OSM-066 17.2.1); test the Fusemate before use, and don't fit a permanent fuse if it blows (OSM-070 12.3, 12.6). An open-circuit fault can be backfed from the other end (OSM-067 11.4).
- Poles. Inspect a pole before you climb it: date mark, birthmark depth, damage, hammer and prod test (OSM-066 15.4 to 15.6).
How accurate is it?
- Every operation re-solves the network phase by phase: which source feeds each conductor, parallels, short circuits and dead sections. Voltage indicator readings come from the phasors: 240 V phase to neutral, about 415 V between phases, and about 21 V between like phases of Mill Lane and Station Road (their HV sources are taken as 5° apart). The indicator shows LED steps of 12, 24, 50, 120, 230, 400 and 690 V, like a two-pole LV voltage indicator.
- A dead conductor that still has customers' loads connected sits at neutral potential, so it reads about 240 V to a live phase. That's why you confirm both sides live before reading the ladder.
- Loads are 2 kW per customer after diversity, balanced across the phases (about 2.8 A per customer per phase). Any fuse or transformer loaded above its rating counts as an overload: Control will not accept the arrangement (OSM-027 9.1.3). A fuse well above its rating also operates in the game, after about an hour at 1.6 times its rating or about 10 minutes at twice it, which is a simplified version of a BS 88 fuse's time-current curve. Transformer full-load current is worked out at 400 V (about 144 A for 100 kVA, 722 A for 500 kVA).
- Faults: closing onto a fault blows the smallest fuse on each path from the sources; a link has no fault rating, so closing one onto a fault is an arc flash. Customer minutes lost count every minute every customer is off.
Map symbols follow SSEN's Electric Office guide (REF-NET-COM-011): substation, pole, pole-mounted transformer, link box and pillar. The guide has no symbol for an LV street cabinet, so that one is the simulator's own. The red arrows mark open points, as on DNO diagrams.
Things it simplifies: the people on site do what you say, fuse ratings and loads are typical rather than from one company's tables, and switching times are rounded. It is a training game, not a substitute for your company's safety rules, authorisation or approved procedures.