Network control room simulator
About this simulator
Sit at the 11 kV control desk for a UK distribution network. Faults trip circuit breakers and reclosers; you read the alarms, send crews, switch by SCADA, sectionalise to find the fault, back-feed customers without overloading anything, and make it safe for repair. Every current, voltage and trip time is calculated from the network.
How it works
You run the 11 kV desk for Ashcombe, a 33/11 kV primary substation with two 7.5/15 MVA transformers and a sectioned 11 kV busbar, normally run with the bus section closed (transformers in parallel). Three underground ring circuits feed the town (F1, F2 and F5, with normally open points between them and to Brook primary, which is fed from a different grid group). Two overhead circuits run out across the hills (F3 Ridgeway with a PMCB recloser, ASLs and spur fuses; F4 Hill Farm with a voltage regulator, a pole-mounted circuit breaker for the quarry and a back-feed from Brook).
- Read the desk. Alarms arrive with the protection element that operated and the current it saw. Telemetered switches (circuit breakers, the PMCBs, the regulator and the remote-controlled ring main units) show their real state. Everything else shows what control last knew: if a fuse blows or an ASL drops, you will not know until customers ring or a crew reports it.
- Switch. SCADA commands go through in about 12 seconds. For everything else, send a crew: they drive there (at road speed from where they are), then do the job, which takes as long as it would on site.
- Find it and make it safe. Read fault passage indicators, sectionalise, patrol overhead lines, test cables, then have the faulty section isolated, earthed and handed over for repair.
- Restore. Back-feed from the next circuit or from Brook without overloading anything, without paralleling different grid groups, and with 11 kV voltages inside ±6 % (the ESQCR limit at HV supply terminals, used here as the planning limit across the network).
Each shift gives up to three stars: one for finishing it (faults made safe, everyone who can be restored back on, nothing overloaded, voltages in limits), one for doing it without safety strikes or slips, and one for doing it with no hints and with customer minutes lost (CML) within par. Three safety strikes and the duty manager takes the desk.
Rules it checks
These follow SSEN's Operational Safety Manual (OSM) and Operational Safety Rules where they cover the point, with SPEN's regulator policy for the voltage regulator. Wording follows SSEN's approved control terms (OSM-028): PMCB, Non-Auto, DOEF, Replace HV Fuses, Replace Links, Permit-to-Work. Other DNOs differ in the detail, so treat them as typical UK practice rather than your company's rules. The rules are checked when you act, not only when something goes wrong.
- Re-energising. Before the first manual reclose after a lockout, SSEN waits 20 minutes between 06:00 and 22:00 and 5 minutes overnight (OSM-014 Table 10.1, OSM-020 Table 7.1). In abnormal weather the duty manager can allow an immediate reclose. Reliable evidence (FPIs read, a patrol, a site report, automation) lets you restore healthy sections straight away (OSM-064 13.8). Switch the circuit breaker or PMCB to Non-Auto first (OSM-020 9.1; auto-reclose counts as system automation, OSM-036 8.3, 9.2). An overhead circuit gets one manual reclose, then a patrol (OSM-020 12). Never re-energise where damage or contact has been reported (OSM-014 10.3). Staff must be clear of substations and plant on the circuit (OSM-064 13.15). Indoor and enclosed busbars are inspected on site before they are re-energised (OSM-014 15.3.1).
- Hand operation. Close on to a possible fault from a circuit breaker by remote control where you can (Operational Safety Rules 3.6.7). Before anyone operates HV fuses (DOEFs), links or an ABSD by hand, the upstream circuit breaker or PMCB goes to Non-Auto. A second manual reclose needs new evidence or sectionalising (OSM-020 12). HV fuses and links are only replaced once the network beyond has been patrolled with no obvious damage, or after the reclose delay with no damage reports (OSM-014 16.4).
- Switchgear ratings (OSM-034 Appendix A, 11 kV).
- Category 1 ABSDs (interrupter heads) break up to 400 A of load or loop current.
- Category 2 ABSDs (arcing horns) break 20 A of load, and loop current up to their full-load rating or 300 A, whichever is less.
- Expulsion fuses break about 500 kVA of installed transformers (OSM-034 10.4.5, Appendix B). ASLs are dead-break links: remove them only when the spur is dead.
- Every ABSD here has a green triangle, because the fault level is inside its 7.5 kA peak fault-making rating (OSM-034 Appendix C).
- Switchgear under an operational restriction is not operated live (OSM-034 8.4, OSM-037).
- The regulator's disconnects are off-load devices.
- Isolation, earthing and the Permit-to-Work. Isolate at an isolating device in the isolating position: an ABSD, links, removed HV fuses or a racked-out CB. Opening a PMCB is not isolation (Operational Safety Rules section 2, definition of Isolated, and 4.1.1(b)). Each point of isolation gets a Safety Lock and Caution Notice, and its remote control is disabled, so SCADA cannot close it while the Permit-to-Work is out (Operational Safety Rules 4.2.2, 4.2.4; OSM-036 9.3). Switch the F2 automation out before switching or earthing on its scheme (OSM-036 9.2, 9.3). Then the crew proves the section dead, applies circuit main earths (and spikes the cable on underground work), and the Senior Authorised Person issues the Permit-to-Work with Control's consent (OSM-017 10.1.4).
- Cancelling a Permit-to-Work. When the repair team finish and return the permit, a crew cancels it, removes the circuit main earths and the Safety Locks and Caution Notices, and the section can be switched back in (OSM-017 10.1.5). Trying to cancel while the work is still going on is a slip.
- Low conductor reports (OSM-081). If protection has operated and a low conductor is then reported, open the nearest available upstream device by remote control at once (11.3.4), inform the emergency services and the highway authority (11.3.2), and send the first crew to secure the site (11.1.1). Never replace fuses or links until the damage is isolated (11.1.4).
- Grid groups and regulators. Ashcombe and Brook are fed from different 132 kV groups, about 6° apart, so transfers between them are break-before-make. Before you back-feed through the voltage regulator, put it on neutral and take it out of auto. A forward-locked regulator fed from the wrong end runs its taps to the limit.
- Interruptions. Ofgem counts an interruption of 3 minutes or more as a customer interruption (CI) and adds its minutes to CML. Shorter ones, including a successful auto-reclose, are short interruptions. Customers restored for under 3 minutes and then lost again count as off throughout.
Instructions in the log follow the OSM-017 pattern: the instruction, the read-back, then the confirmation. Operational restrictions are stated when they are given.
How accurate is it?
Nothing is scripted except the fault itself, customer phone calls and grid events. The whole network is solved as one AC circuit every time anything changes, and protection, loads and heating run on the solution.
- Load flow: complex nodal analysis with constant-power loads, transformer taps and the regulator as off-nominal ratios. Loads follow domestic, commercial, industrial and farm daily profiles by season. Back-feeds, voltage drop and circulating currents come out of the maths.
- Faults: symmetrical components for three-phase, phase-phase and phase-earth faults with fault resistance. The 11 kV neutral is resistance earthed (6.35 Ω per transformer, about 1 kA each), so earth fault currents are lower than phase faults and fall along the line. The 11 kV bus fault level is about 6.3 kA (about 120 MVA) three-phase with both transformers in parallel (about 3.4 kA from one), and about 1.9 kA phase-earth. That is under SSEN's 150 MVA threshold for opening the bus section before a reclose (OSM-014 9.1) and under the 7.5 kA peak making rating of the ABSDs.
- Protection: IEC 60255-151 inverse curves (standard, very and extremely inverse), instantaneous elements, sensitive earth fault (this sim locks out on SEF because an SEF operation is most likely a conductor on the ground, OSM-020 Table 8.1; some DNOs reclose on SEF), auto-reclose with dead times, reclaim time and sequence co-ordination, ASL counting, expulsion and back-up fuse melting curves, three-phase fault passage indicators (phase and earth fault). FPIs self-reset after 4 hours here; that is an assumption, and SSEN resets them by hand (OSM-036 9.6). Feeder relays are modelled on GE MiCOM P14x feeder management relays; the settings are typical UK values, not any DNO's setting sheet.
- Ratings: cable and overhead line ratings in amps from SPEN's ratings document (Al XLPE and PICAS cables laid direct; Hazel, Rabbit, Dog and Oak conductors), summer and winter, with cyclic ratings for emergencies. Lines heat with a time constant (an hour for cable, ten minutes for overhead line), so a short overload is allowed but a long one is not.
- Transformers: hot-spot temperature by the IEC 60076-7 two-time-constant method (oil and winding), alarm at 105 °C and trip at 130 °C. Automatic voltage control on 11.1 kV ±1.25 %.
- Cold load pickup: after a long outage, heating and fridges all start together, so load comes back up to about 60 % above normal and decays over half an hour.
What it simplifies: crews drive at an average 40 km/h with a few minutes to get going; job times are typical, not timed on site; ring main units are shown with ring switches and a tee-off only (no earth switch positions to operate); there is no 33 kV network to manage beyond losing and getting back the grid supply; isolation, earthing and issuing the Permit-to-Work are one crew job (the log lists each step), and so is cancelling it; repair times are typical (about 1.5 hours for an overhead span, 5 hours for a cable joint).