HV switching and safety documents simulator

The switching procedures and safety documents follow SSEN Distribution's Operational Safety Rules and Operational Safety Manual. If you switch for another DNO, your company's practice may differ in places.Follows SSEN’s switching procedures; other DNOs’ practice may differ. About this simulator

About this simulator and how it works

Switch an 11 kV network the way a UK distribution network operator does: carry out Control's schedule, isolate, prove dead, earth, issue Permits-to-Work, Sanctions-for-Test and Limitation-of-Access, then restore. Every trip, bang and customer minute lost comes from a real load flow and fault calculation.

How it works

You are an Authorised Person on one network: a town ring of five secondary substations (ring main units, one automated, one older oil RMU, a teed transformer and a brewery with its own CHP generator) fed from Ashby Primary, and a rural overhead feeder from Brook Primary with an auto-recloser, an ASL-protected spur, EDO fuses, pole transformers, a pole-mounted circuit breaker, a voltage regulator bank and air break switch disconnectors. The overhead line meets the ring at a normal open point (AB3 at pole 88).

  • Levels 1 and 2 give you Control's schedule. Drive to the site, ring Control, read the instructions back, do them in order, report, and move on. Level 2 adds safety documents.
  • Level 3 makes you write the switching schedule: tap the operations in order on the drawings, add Control's actions and the document, and submit it. Control then instructs you from your own schedule.
  • Level 4 hides traps: a wrong step in Control's schedule to query, generation that can backfeed, an operational restriction, a dropped ASL, and a regulator whose position indicator lies.

Each job gives up to three stars: one for completing it with the network safe and back to normal, one for no safety strikes or slips, and one for keeping customer minutes lost within par with no hints. Three strikes stop the job; some mistakes (earthing a live line, bypassing a regulator off neutral) stop it at once.

The rules it checks

The rules follow SSEN Distribution's published Operational Safety Rules (2022) and Operational Safety Manual, which are based on the ENA Model Distribution Safety Rules. Rule numbers marked OSR are SSEN's rules (from section 4 on they match the ENA model rule numbers); OSM numbers are sections of SSEN's Operational Safety Manual. Where SSEN's public documents are silent, the simulator uses common DNO practice and says so.

  • Control's instructions. Switching is done only on Control's instruction from an approved Switching Schedule, read back, and reported without delay (SSEN OSR 3.6, 3.7; OSM-017). Instructions use SSEN's approved phrases (OSM-028), such as "Open", "Earth", "Remove Earth", "Apply Isolation", "Test and Earth" and "Switch to Non-Auto". If a step looks unsafe, query it before you carry on. Doing something that isn't your next instruction is caught; you can ask Control to amend the schedule, and added items take decimal numbers such as 9.1 (OSM-017 11.4.1).
  • Isolation. Every point of isolation is locked with a Safety Lock and has a Caution Notice, and the keys go in the Key Safe (SSEN OSR 4.2). On an RMU with a single operating mechanism the Safety Lock goes on the selector in the OFF / EARTH position, so it isn't disturbed until the switch is restored and the earth switch can be operated without removing it; once in EARTH, the earth switch is locked there with an 'X' type operational lock (SSEN OSM-026 10.4.1). Carriers and links that are removed are kept safe. Remote control and automation must be made inoperative: a motor actuator to LOCAL with its selector locked, the auto-restoration scheme switched out (SSEN OSR 5.2). A recloser is not a point of isolation.
  • Proving dead and earthing. Overhead: prove the voltage indicator, test, prove again, then apply portable earths. An RMU is proved dead by closing its earth switch, which is fault-making rated; VPIS neons are not a test for dead (this follows SSEN's switching manual; check your own company's rules). Circuit Main Earths go at, or between, each point of isolation and the work (SSEN OSR 4.1.1(c)); Additional Earths are the gang's, applied after issue and removed before clearance.
  • Cable identification. SSEN identifies and spikes a cable under a Sanction-for-Test (OSM-062 12.7 and Appendix B): the earth comes off at one end to inject the identifier signal, Control is told before and after, the spike is fired with the identifier still connected, and the Circuit Main Earth goes back on before the identifier comes off. The SFT is cleared and then the Permit-to-Work is issued.
  • Safety documents. A Permit-to-Work goes to an appointed Competent Person, a Sanction-for-Test only to an Authorised Person, and a PTW on the same apparatus must be cleared first. What is written must match what is on the ground: every point of isolation and every Circuit Main Earth, keys in the key safe. A faulted or underground cable is identified and spiked at the point of work before the permit.
  • Plant. EDO fuses and ASLs are not load-break devices: break the LV first or use a load-break tool. ABSDs have a load-breaking rating. A step-voltage regulator is bypassed only on neutral, confirmed by the position indicator and the neutral lamp, with the control OFF (Cooper VR-32 and Siemens MJ-4A instructions). Any generation that can feed the work is a point of supply and must be isolated and locked (SSEN OSR 4.1.1(b)); on another party's system that is done by their own Authorised Person and recorded on an Isolation Certificate (SSEN OSM-087 12.4; Distribution Code DOC8). Some companies, such as SSEN, need fewer LV backfeed precautions for small type-tested LV generation. Before fuses, ASLs or links are closed by hand, the upstream auto-reclosing device goes to non-auto. That is SSEN practice (and SPEN's and ENWL's), although SSEN's public manual doesn't write it down.

How accurate is it?

  • The network is solved as a complex nodal circuit after every operation: voltages, currents in every cable and switch, and the current a switch breaks or makes. Cable and line impedances are typical for 185 mm² XLPE, 0.15 in² PILC, 100 mm² AAAC and 50 mm² ACSR. The primaries are 180 and 120 MVA fault level.
  • Earthing onto a live circuit is a three-phase fault: the fault current is calculated and the protection clears it on IEC standard inverse curves (with instantaneous elements), fuses blow on an approximate melt curve, and the recloser (two fast trips, then two on the inverse curve) and Brook F4 reclose to lockout, and the settings are graded so the device nearest the fault clears it. A recloser closed by hand onto a fault locks out instead of reclosing. ASLs count the recloser trips and drop out in the dead time, as they do in service.
  • Customer minutes lost and customer interruptions are counted in the style of Ofgem's IIS: only interruptions of 3 minutes or more count. They are unweighted here (the real scheme halves planned, pre-arranged interruptions).

Map symbols follow SSEN's Electric Office guide to symbols (REF-NET-COM-011). The guide has no symbols for ring main units, normal open points or regulators, so those are the simulator's own.

Things it simplifies: it is three-phase balanced, the protection settings are typical rather than one company's, and the people on site do what you say. It is a training game, not a substitute for your company's safety rules, authorisation or a real switching schedule.