Part P: what electrical work is notifiable in England?

Notifiable electrical work in England: a new circuit, a new consumer unit, or work in a special location, shown as the space around a bath from the floor to 2.25 metres high and 0.6 metres out from the edge of the bath
Beginner

Part P of the Building Regulations covers electrical safety in homes in England. It applies to all electrical work in a dwelling, but only some of it is notifiable, meaning building control has to be told about it. This guide explains which jobs are notifiable, from the wording of the regulations themselves.

What Part P requires

Requirement P1 says reasonable provision must be made in the design and installation of electrical installations to protect people operating, maintaining or altering them from fire or injury. It covers low and extra-low voltage installations:

  • in or attached to a dwelling;
  • in the common parts of a building serving one or more dwellings (but not supplies to lifts);
  • in an outbuilding, such as a shed or garage, or in a garden, that gets its electricity from a dwelling.

This applies whether or not the work is notifiable. Approved Document P, the government's guidance on Part P, points to BS 7671, the IET Wiring Regulations, as the way to design and install safely.

When Part P came into force

Part P came into force on 1 January 2005, in both England and Wales. It was added to the Building Regulations by the Building (Amendment) (No. 2) Regulations 2004. From that date, almost all electrical work in a home had to be notified to building control, or done by an electrician registered with a competent person scheme who could self-certify it.

The 2005 rules only let you skip notification for minor work:

  • replacing a socket-outlet, switch or ceiling rose;
  • replacing a damaged cable on a single circuit;
  • re-fixing or replacing enclosures, or adding mechanical protection, without changing the circuit's protective measures;
  • adding light fittings and switches to an existing circuit, adding sockets and fused spurs to an existing ring or radial, or installing or upgrading bonding, but only if the work wasn't in a kitchen or a special location (around a bath or shower, a swimming or paddling pool, or a sauna) and wasn't on a "special installation" such as garden lighting or power, electric floor or ceiling heating, a generator or extra-low voltage lighting.

So under the original rules, adding a socket in a kitchen or a light in the garden was notifiable.

What changed in England in April 2013

From 6 April 2013, the Building Regulations &c. (Amendment) Regulations 2012 replaced that approach in England with the short list in regulation 12(6A) below: a new circuit, a replacement consumer unit, or an addition or alteration to a circuit in a special location. Work in kitchens and gardens stopped being notifiable in its own right. The same year, the government published a new edition of Approved Document P. The 2012 regulations don't apply to homes in Wales, which kept the older, wider rules.

Notifiable work in England

Regulation 12(6A) of the Building Regulations 2010 says electrical work in a home is notifiable if it consists of:

  1. installing a new circuit, such as a circuit for an EV charger, a shower, a cooker, an outbuilding, or a new socket or lighting circuit;
  2. replacing a consumer unit (the fuse box);
  3. any addition or alteration to existing circuits in a special location.

What counts as a special location

  • In a room with a bath or shower, the space around the bath or shower. Vertically, it runs from the floor to 2.25 m, or up to the shower head if it's fixed higher than that. Horizontally, it runs 0.6 m out from the edge of the bath or shower tray. Where there's no tray, as in a wet room, it runs 1.2 m from the centre of the shower head.
  • Any room containing a swimming pool or a sauna heater.

So adding a socket in a bedroom on an existing circuit isn't notifiable, but extending a circuit to a light within 0.6 m of the bath is.

Examples

JobNotifiable in England?
New circuit for an electric shower, cooker, EV charger or heat pumpYes: new circuit
Replacing a consumer unit or fuse boxYes
Rewiring a houseYes: new circuits
A new circuit to a garden office or shedYes: new circuit
Adding a light or fan to an existing circuit within the bath or shower zone described aboveYes: special location
Adding a socket or light point to an existing circuit in a living room, bedroom or kitchenNo, but it must still be safe and meet BS 7671
Replacing a socket, switch or light fitting like for likeNo
Replacing a damaged cable on one circuitNo

Kitchens aren't special locations in England: the current rules only single out the space around baths and showers, and rooms with swimming pools or saunas.

Who can do notifiable work

A registered electrician

An electrician registered with a competent person scheme for this work can self-certify it. Schedule 3 of the regulations lists the scheme operators for electrical installations in dwellings: Blue Flame Certification, Certsure (which runs NICEIC and ELECSA), NAPIT and OFTEC. Within 30 days of finishing, the electrician must give you a certificate that the work complies and give building control a notice or a copy of it. You should also get an Electrical Installation Certificate with the test results.

Doing it yourself, or using someone who isn't registered

The law doesn't stop you doing notifiable work yourself. But before you start you must give your local authority building control a building notice or a full plans application, and pay their fee. They'll inspect the work and may want test results, so in practice you need to be able to test and certify it to BS 7671, or pay someone who can.

What can I do with a Part P qualification?

There's no qualification that licenses you to do "Part P" work. Part P is a requirement in the Building Regulations, not a licence. The "Part P courses" sold to electricians, such as City & Guilds 2383 (and the older 2393), Building Regulations for Electrical Installations in Dwellings, teach how the Building Regulations apply to electrical work in homes. City & Guilds describes 2383 as CPD, or underpinning knowledge for electricians working towards a full qualification. Passing one doesn't let you sign off notifiable work on its own.

What lets you self-certify is registering your business with a competent person scheme. The IET explains that the competence the schemes check is set by a common standard, the EAS, and can be met through a mix of qualifications and experience. For example, NICEIC's Domestic Installer scheme asks for:

  • a Qualified Supervisor with at least 2 years' responsibility for electrical work, with certificates of their technical qualifications;
  • a current copy of BS 7671 and HSR25 (the HSE guide to the Electricity at Work Regulations 1989), and a written safe isolation procedure;
  • examples of domestic work you've done and certified in the last 12 months, for an office and site assessment;
  • at least £2 million public liability insurance, and a surveillance assessment every year after you join.
Is the job notifiable? No: no noticemust still meet BS 7671 Yes: are you registered with a scheme? Yes: self-certifycertificate to youwithin 30 days No: before you startbuilding notice, or athird-party certifier noyes
A course certificate doesn't change this. Only scheme registration lets you self-certify.

What you can do without registering

  • Non-notifiable work, such as the jobs marked "No" in the table above, with or without a course. It must still be safe and meet BS 7671.
  • Notifiable work, through building control. Give them a building notice or full plans before you start and pay their fee, as described above.
  • Notifiable work, through a third-party certifier. A registered third-party certifier, appointed before the work begins, inspects and tests it and certifies it. They can't be the person who did the work.

The IET points out that there's no legal requirement to join a scheme. Many electricians join because it saves a building control fee and visit on every notifiable job.

Why it matters

  • The certificate shows the work met the Building Regulations. Buyers' solicitors usually ask for it when you sell, and missing paperwork can hold up a sale.
  • Check a registered electrician on the scheme's own website before you book. Registration is per business and per type of work.

Wales, Scotland and Northern Ireland

This guide covers England. Wales has its own version of the Building Regulations and still uses the pre-2013 approach: adding lights or sockets to an existing circuit is only exempt from notification if it isn't in a kitchen or a special location and isn't on a special installation such as outdoor lighting or power. Check the Welsh Government's guidance. Scotland uses building warrants under the Building (Scotland) Regulations, and Northern Ireland has its own building regulations.

Sources

The main references behind this guide. Numbers we worked out ourselves, such as the code outputs, come from running the code.