The low voltage (LV) network is the last part of the journey: from the local substation, along the street, to the cut-out where your supply comes in. It's mostly hidden under pavements and verges, but knowing how it's put together explains a lot about power cuts, supply voltage, earthing and why "the neutral" can be the most dangerous conductor on it.
From the substation to the street
A distribution substation steps 11 kV down to 400 V three-phase, 230 V phase to neutral. Its LV board has several outgoing ways, each protected by a set of three fuses, one per phase. Each way feeds a feeder or main: a four-core cable (three phases and a combined neutral and earth on modern cable) running along the street.
Homes are connected by a service cable teed off the main with a service joint. Single-phase homes are spread across the three phases, roughly one in three on each, so the load on the feeder is balanced as well as it can be.
Link boxes, pillars and normally open points
The ends of neighbouring feeders, often from different substations, are brought together in a link box (underground, under a small cover in the pavement) or a pillar (a green cabinet at the roadside). Inside are removable links or fuses for each phase and the neutral. Normally some are left out, making a normally open point (NOP), so each feeder is radial and fed from one end only. That keeps the fault levels and protection simple.
When a cable fails or work is planned, staff can move the open point: take links out to isolate the faulty section, and put links in at the open point to back-feed the healthy part from another feeder, so fewer customers are off. Before any links go in, the two sides must be checked to be on the same phases and rotation, or closing them would join two different phases.
Overhead LV
In rural areas the LV network is often overhead: a pole-mounted transformer, then insulated aerial bundled conductors (ABC) or older open bare wires on poles, with services dropping to each house. The same ideas apply, with fuses at the transformer and links on poles.
The cut-out and service fuse
The service cable ends at the cut-out, the sealed box where your supply starts. It holds the service fuse, commonly 60 A, 80 A or 100 A in a home, which protects the service cable. On the customer side are the meter tails, the meter and often an isolator. The service cable and the cut-out, with its service fuse, belong to the network operator, and the meter to the supplier's meter operator, so only they can break the seals or remove the fuse. If the house is earthed from the supply, the earth terminal is on or next to the cut-out too.
How homes are earthed
| System | How it works |
|---|---|
| TN-C-S (PME) | The cable has a combined neutral and earth (PEN) conductor, earthed at the substation and at points along the network. The customer's earth terminal is connected to the neutral at the cut-out. The most common arrangement for homes |
| TN-S | A separate earth, usually the lead sheath or steel armour of older paper-insulated cables |
| TT | No earth is provided by the network; the customer has their own earth electrode, and RCDs give the fault protection |
The full picture, including how each one affects testing, is in earthing systems explained.
Supply voltage limits
The law says the supply to homes is 230 V, allowed to vary from 6% below to 10% above: 216.2 V to 253 V (ESQCR regulation 27). The voltage drops along a feeder as load increases, so homes at the far end of a long, busy feeder see the lowest voltage at peak times. Solar panels and batteries exporting on a lightly loaded feeder can do the opposite and push the voltage up.
Neutral faults: why a broken neutral is dangerous
A broken or high-resistance neutral is one of the most damaging faults on the LV network. SSEN's procedures list the usual causes: a failed neutral conductor in a cable or joint, a jointing error, a mobile generator connected wrongly, or loss of the neutral or earth connection at a substation, sometimes from theft.
With a healthy neutral, each house gets 230 V whatever its neighbours use. Lose the neutral and the loads on different phases end up in series across the 400 V between the phases. Take one house using 2 kW on L1 and one using 6 kW on L2 (simple heating loads). Their resistances are 230² ÷ 2,000 = 26.45 Ω and 230² ÷ 6,000 = 8.82 Ω. In series across 400 V they pass 400 ÷ 35.27 ≈ 11.3 A, which puts about 300 V across the lightly loaded house and about 100 V across the heavy one. Real networks are more complicated, but the pattern is the same: lights burning unusually bright in one house and dim in the next, and electronics damaged by overvoltage.
On a PME supply there's a second danger: if the combined neutral and earth breaks, the earthed metalwork in the installation can rise towards line voltage. That's why PME is subject to extra rules, such as main protective bonding sized for PME, and why some locations, like EV charge points outdoors, need special measures. If you see flickering, very bright or very dim lights, or get a shock from metalwork, call the network operator on 105.
Switching and testing on the LV network
Network staff work on the LV network under their company's safety rules. From SSEN's public procedures:
- Fuses and links are put in or taken out with approved handles, in one positive, uninterrupted movement so both contacts break or make together.
- Voltage and polarity are checked with approved voltage indicators before and after any fuse or link is put in or taken out.
- If the condition of a circuit isn't known, a device such as a Fuse Mate or Rezap is used to make it live first. These take the place of the fuse and switch the circuit on in a controlled way, so if a fault is still there they trip, rather than the operator closing a fuse onto it.
- After alterations, the supply, polarity and phase rotation are confirmed, including at the customer's cut-out.
You can practise moving open points and phasing out in the LV switching simulator, and testing a cut-out before and after work in the supply point testing simulator.
Going deeper
Cable types you'll find
Older mains are paper-insulated, lead-sheathed (PILC), often with steel armour. Modern mains and services are XLPE-insulated with a combined neutral and earth made of wires laid round the cores, such as Waveform cable for mains and CNE concentric cable for services. Split-concentric service cable is different: its neutral and earth wires are kept apart (SNE). Jointing between old and new types needs care to keep the neutral and earth continuous.
Phasing out
Before two LV circuits are joined, at a link box, a pillar or a new joint, the voltage between each phase on one side and each on the other is measured. Matching phases read close to 0 V; different phases read about 400 V. Only when every pair is confirmed, and the rotation matches, are links inserted.
Fuse discrimination on feeders
The substation fuse on each way has to be big enough for the feeder's load but small enough to clear a fault at the far end of the cable. On very long feeders the far-end fault current can be too low to blow the fuse quickly, which is one reason network operators limit feeder lengths, and why the fuse sizes are chosen from the transformer rating and the cable size.
Sources
The main references behind this guide. Numbers we worked out ourselves, such as the code outputs, come from running the code.
- SSEN Distribution PR-NET-OSM-027: Low voltage system switching and earthing (2023)
- SSEN Distribution PR-NET-OSM-071: Management of neutral faults on the low voltage system (2023)
- SSEN Distribution PR-NET-OSM-069: Testing at low voltage supply points (2023)
- The Electricity Safety, Quality and Continuity Regulations 2002, regulation 27: declared voltage and permitted variations