High voltage (HV) means more than 1,000 V AC. On a distribution network that's usually 11 kV, 33 kV or 132 kV, and at those voltages you don't have to touch a conductor to be hurt: getting too close is enough. So HV work follows a strict, written system of work, set out in each network company's operational safety rules. This guide explains how that system works, using the public rules of SSEN Distribution as the example. Other UK network operators' rules are built on the same industry model and work in much the same way, but always follow the rules of the company you're authorised by.
Who is allowed to do what
Nobody works on HV just because they're qualified. Each person is assessed and appointed in writing for specific duties:
| Role | What it means |
|---|---|
| Competent Person | Has enough technical knowledge and experience to avoid danger. Can be nominated to receive and clear specified safety documents, such as a Permit-to-Work for the job they are doing |
| Authorised Person | An experienced Competent Person appointed to carry out specified duties, such as switching, and which may include issuing a Limitation-of-Access or receiving a Sanction-for-Test |
| Senior Authorised Person (SAP) | An Authorised Person appointed for further duties, including issuing and cancelling safety documents such as a Permit-to-Work |
| Control Engineer | Runs the network from the control centre. No HV isolation or reconnection may start without their sanction |
Plan first: the switching schedule
For planned HV work, the operations are written down in advance as an approved switching schedule: every step, in order, with the exact location and name of each item of switchgear. On the day, the control engineer gives each instruction, and the Authorised Person writes it down and reads it back in full before doing it. Separate operations are given separately: "open" and "apply earth" are two instructions, not one. Each one is confirmed back to control when it's done.
The order matters. Every point of isolation is confirmed first. Only then are the earths applied, and only once the earths are confirmed does control agree to a safety document being issued. Putting the circuit back works the same way in reverse.
The six conditions before anyone works
All HV equipment is treated as live, including equipment that's damaged or has faulted, until it has been made safe in this way. The person issuing the safety document is responsible for making sure each condition is met, in the right sequence.
- Dead. The circuit is switched out.
- Isolated and locked off from every point it could be made live from, including voltage transformers and other back-feeds. Where there's a locking facility, a Safety Lock is fitted: a lock used only for safety and different from every other lock on the system. A Caution Notice goes on every point of isolation. Where a circuit is controlled only by fuses or links, they're removed and kept safe.
- Earthed at every point of disconnection, or between those points and the work. Where possible that's done with an earth switch or a circuit-breaker in the earth position, locked there. Otherwise the conductors are first checked with an approved voltage tester to confirm they're not live, then earthed with portable earthing leads on an insulated pole.
- Screened and Danger Notices fixed on, or next to, anything nearby that's still live, so nobody goes to the wrong panel.
- Identified at the point of work by an approved method. For an underground cable that means proving that the cable in the hole really is the one that's been made dead, using cable identification equipment and, where required, spiking it.
- Released for work with a safety document, explained to and understood by the person receiving it.
Circuit Main Earths and Additional Earths
The earths applied before a safety document is issued, at positions written on it, are Circuit Main Earths. They stay on for the whole job and are locked where there's a facility. Earths applied after the document is issued, for example right at the point of work, are Additional Earths, and they're controlled by the person in charge of the work. Earthing both sides of the work means that if the circuit were accidentally made live, or a voltage were induced from a nearby line, the fault current would flow to earth through the earthing equipment, not through a person.
The three safety documents
| Document | What it's for |
|---|---|
| Permit-to-Work (PTW) | Says exactly which HV apparatus has been made safe to work on, and what the work is. Issued by a Senior Authorised Person to a Competent Person, who keeps it on them until the work is finished |
| Sanction-for-Test (SFT) | Says which apparatus has been made safe for testing, such as a pressure test on a new cable, and the conditions for that test. It's received by an Authorised Person. Testing may mean removing earths and applying voltage, so any Permit-to-Work on the same apparatus has to be cleared and cancelled, or suspended, first |
| Limitation-of-Access (LOA) | Sets the limits of work that isn't on HV apparatus but has a danger that verbal instructions don't cover, for example working near, but outside the safe clearance from, exposed live HV conductors |
A safety document is not just paperwork. It's only issued after the issuer and recipient have both been to the point of work and agree on exactly what is safe, what the job is and where its limits are. The recipient signs to say they understand it, and from then on they are responsible for their working party staying within it.
Finishing the job and restoring supply
When the work is done, the recipient clears the document: they confirm everyone has been withdrawn, all tools and Additional Earths are removed, and the apparatus is ready. The Senior Authorised Person then cancels it. Only then, on the control engineer's instruction, are the Circuit Main Earths removed, then the Safety Locks and Caution Notices, and finally the circuit is switched back in. Each step is confirmed back to control before the next is instructed.
Low voltage work on the network
On the LV network (up to 1,000 V AC) the rules are different but just as strict: work is normally done by authorised staff using approved procedures, fuses and links are removed to isolate, and the voltage, polarity and phase rotation are checked before and after any fuse or link goes back in. See the LV network explained for how that part of the system works.
You can practise switching an 11 kV network, applying earths and issuing permits in the HV switching simulator.
Going deeper
Why the earth switch is preferred
An earth switch or a circuit-breaker used as an earth is rated to close onto a fault. If the circuit turned out to be live, or became live while it was being earthed, the switchgear would make the fault current safely inside its enclosure. A portable earth applied by pole can't do that, which is why the conductors are proved not live first, and why portable earthing equipment has to be of an approved, rated type.
Induced voltages
A dead overhead line or cable that runs alongside a live one can have a voltage induced in it by the live circuit's electric and magnetic fields, even though it's isolated at both ends. Earthing at the points of isolation and at the work site drains that voltage and keeps the conductor near earth potential. It's one reason work on lines near other live circuits needs extra earths and careful planning.
Exceptions
The rules allow a few exceptions, such as approved live-line working on overhead lines, live washing of insulators, or a single Circuit Main Earth at the point of work for some overhead line jobs. They are only used under approved procedures and at the discretion of a Senior Authorised Person.
Sources
The main references behind this guide. Numbers we worked out ourselves, such as the code outputs, come from running the code.
- SSEN Distribution Operational Safety Rules 2022 (PR-NET-OSM-006): definitions and Rules 4.1 to 4.8
- SSEN Distribution PR-NET-OSM-017: Switching schedules and switching log books (2023)
- The Electricity at Work Regulations 1989, regulations 12 to 14 (isolation, precautions for work on dead equipment, live working)