Safe isolation cheat sheet

Printable one-page safe isolation procedure: equipment, the steps in order, and which conductors to test on single-phase and three-phase supplies.

Full guide

Safe isolation cheat sheet ohmandtoken.com

You need

  • A two-pole voltage indicator to GS38 and BS EN 61243-3 (not a multimeter or non-contact tester).
  • A proving unit.
  • A lock, your own key, and a warning notice.

The steps

  1. Get permission and identify the circuit. Don't trust labels alone.
  2. Isolate, and check for other sources (PV, batteries, generators, UPS).
  3. Lock off, keep the key, fit a warning notice.
  4. Prove the indicator on the proving unit.
  5. Test dead at the point of work, every combination.
  6. Prove the indicator again.
  7. Start work. The lock stays on until you're finished.

Which conductors to test

SupplyTestsNumber
Single-phaseL–N, L–E, N–E3
Three-phase with neutralL1–L2, L2–L3, L3–L1, L1–N, L2–N, L3–N, L1–E, L2–E, L3–E, N–E10

The law

  • EAWR 1989 Regulation 12: means of cutting off and isolation.
  • Regulation 13: precautions so equipment made dead stays dead.
  • Regulation 14: no live working unless it's unreasonable for it to be dead, reasonable to work live, and suitable precautions are taken.

GS38 probes: no more than 4 mm of exposed tip, preferably 2 mm or less, with finger barriers.

Sources:

  • Electricity at Work Regulations 1989 (legislation.gov.uk)
  • HSE GS38
  • Electrical Safety First Best Practice Guide 2

Always check against your own copy of the current documents. Mains work must be carried out by a competent person.