About this simulator
Set IDMT relays, pole-mounted circuit breakers (PMCBs) with auto-reclose, drop-out expulsion fuses and ASLs on real-style 11 kV networks, then fire faults at them and watch what trips. Symbols, terms and control procedures follow SSEN’s Electric Office legend and Operational Safety Manual. Every current comes from a per-unit sequence-network fault calculation; every trip time from the published relay curves.
How it works
There are two 11 kV networks, each fed from a 33/11 kV primary substation:
- Hill End is a rural overhead feeder from Bramley primary. It has a feeder CB with auto-reclose, a midline pole-mounted circuit breaker with auto-reclose (PMCB), drop-out expulsion fuses (DOEF) on the spurs, an automatic sectionalising link (ASL), an air break switch disconnector (ABSD), a voltage regulator, pole transformers and an ABSD normally open point.
- Northgate is a two-transformer primary on 33 kV cable circuits, with a bus section and an underground open ring. The ring has five RMUs with ring switches, fault passage indicators and tee-off CBs on self-powered relays, feeding ground-mounted 11/0.433 kV transformers.
Each job sets you one protection problem on one of them.
- Set. Tap a relay, recloser, fuse or ASL to see its settings. A teal dot marks the ones you can change on that job. Settings move in the steps the real device allows: TMS steps of 0.025 on a MiCOM P14x, plug settings of 50 to 200 % on a CDG11, and the standard K and T link sizes.
- Fire faults. Tap any line, cable, busbar or node to place a fault, then choose its type (three-phase, phase-phase, phase-earth or two-phase-earth), fault resistance and nature: permanent, transient, or one that burns itself clear. You can also choose maximum or minimum fault conditions. The event record time-stamps every trip, reclose, fuse operation and ASL count, and the drawing replays it. Firing faults is free.
- Read the curves. The time-current chart shows the devices that matter for the job, with the fault levels at the fault you placed. Tap it to read each device's time and the gap to the next one.
- Commission. Commissioning runs the job's tests. Fault tests check what really operated. Grading tests check the margin between two devices at the current each one sees. Load tests check that nothing starts under the stated load. A failed commissioning attempt costs one of your three safety points, and losing all three stops the job.
Each job gives up to three stars. You get one for commissioning it, one for doing it without losing a safety point, and one for doing it inside the par time with no hints and no wrong diagnoses. The Investigator jobs start by replaying a real-style mal-operation, which you diagnose before you fix it. The Sandbox lets you change every device on either network and fire anything at it.
What the engine calculates
- Fault currents. The engine solves the positive, negative and zero-sequence networks by nodal analysis, in per unit on a 100 MVA base. It handles any fault position and fault resistance. Dyn11 transformers carry their ±30° phase shifts and block zero sequence, so an LV earth fault appears on the HV side in two lines only. The 11 kV neutral earthing resistors (6.35 Ω, about 1000 A) and the 33 kV grid transformers' earthing resistors (19.05 Ω each, about 1000 A) are in the zero-sequence network, and so is the capacitance of the lines and cables. Pre-fault load current is added by superposition. The fault-level cards follow IEC 60909: maximum uses c = 1.1, cold conductors and the strongest grid; minimum uses c = 1.0, conductors at 70 °C and the weakest grid. Each card shows the per-unit working.
- Relays. Inverse curves follow IEC 60255-151 (SI 0.14/0.02, VI 13.5/1, EI 80/2, LTI 120/1) and IEEE C37.112 (MI, VI, EI, including their electromechanical-style reset). Setting ranges and steps are the published ones: GE MiCOM P14x (TMS 0.025–1.2 in 0.025 steps, SEF 0.005–0.1 In), GE Multilin 350, and the GEC CDG11. The CDG11 data come from the Alstom CDG11 data sheet: 3 s at 10 times setting, plug settings of 50 to 200 % in 25 % steps, a start at 103 to 105 % of setting, and a disc that takes about 9 s to reset at TMS 1 (scaled with TMS here). Values marked typical in the simulator could not be checked against a published source: the P14x IDMT start at 1.05 times setting, and the PMCB and self-powered relay ranges, which are generic. Directional elements use quadrature polarising for phase and −3V0 for earth fault.
- CTs. Each CT has a ratio, class, rated burden and winding resistance. The effective accuracy limit factor is ALF × (Rct + Rb rated) / (Rct + Rb actual). Above it, the relay sees less current than really flows.
- Reclosers and ASLs. The PMCB has separate fast and delayed curves for phase and earth fault, plus SEF. It runs up to 4 trips to lockout with set dead times and a reclaim time. An SEF trip locks out straight away. The ASL counts fault current followed by a dead line for 0.1 s; if the line stays live (a fuse below it cleared the fault) there is no count. It drops out in the dead time after its set count, and its count resets after 25 s (as in Bussmann's ASL data).
- Fuses. EEI-NEMA K and T expulsion links are interpolated through melting points at 300 s (600 s above 100 A), 10 s and 0.1 s. These are typical values: the full ANSI C37.43 table could not be checked against a published copy, so treat them as typical and use the maker’s curve for a real study. Above 0.1 s the melting I²t is constant. Total clearing is the maximum melting time plus about one cycle of arcing. A fuse heats up across a recloser's fast trips and cools between them (a 30 s cooling time constant: a typical assumed value, as published cooling-factor curves vary by link).
- Time simulation. Currents are constant between events, so the engine advances every relay integrator, fuse melt and timer exactly to the next event. It then re-solves the network with the new switching state. Nothing is scripted: the order of operations comes out of the settings.
- Customers. Interruptions of 3 minutes or more count as customer interruptions (CI), as in Ofgem's RIIO-ED2 rules. Anything restored sooner, including a whole auto-reclose sequence, is a short interruption. Customer minutes lost (CML) assume an hour to restore.
Grading rules it uses
- Relay to relay: 0.3 s between numerical relays with vacuum CBs, and 0.4 s if either relay is electromechanical. This follows the Network Protection & Automation Guide. Some DNOs accept 0.2 s with modern relays and vacuum CBs.
- Relay over a fuse: 0.4 t + 0.15 s, from the Network Protection & Automation Guide. The guide's t is the fuse's nominal operating time; this simulator uses its total clearing time, which is a little more conservative.
- Fuse to fuse: the downstream fuse's total clearing time must be no more than 75 % of the upstream fuse's minimum melting time.
- Fuse saving: the fast trip (relay plus CB opening) must clear at least 1.35 times inside the fuse's minimum melting time with two fast trips, at the maximum fault current at the fuse's own terminals. Above the current where that fails, the fuse can't be saved and will blow on the fast trip.
- ASL count and pick-up: the count is fewer than the recloser's trips to lockout, and more than the number of trips before a downstream fuse blows. The actuating current is at least twice the spur's load and no more than 80 % of the recloser's earth-fault setting (Bussmann's guidance), so it counts every earth fault the recloser recloses on. SEF trips lock out straight away, so they need no count.
- SEF: 2 s between zones, and no more than 12 s at the feeder CB. This is one DNO's published practice.
- Highset: at least 1.3 times the maximum fault current at the next protective device.
- Reach: a setting of no more than two thirds of the minimum fault current at the end of its zone.
DNO policies differ, so each job says which rule it is testing.
SSEN symbols, terms and procedures
- Symbols and colours follow SSEN's Electric Office Guide to Symbols: 11 kV red, 33 kV green, LV brown, poles as purple dots, pole-mounted transformers as a circle holding two purple circles, substations with a red outline and pink fill, a circuit breaker as a black square (an outline when open), an ABSD as a blade with a black pivot, and fuses and ASLs as two circles with a crossover. A red arrow marks each normally open point (NOP).
- Terms follow OSM Section 4.4 (PR-NET-OSM-028), Switching Terminology and Approved Abbreviations: PMCB, DOEF, ASL, ABSD, FPI, RMU, SEF, NOP.
- Manual reclosing after lockout follows OSM Section 2.10 (PR-NET-OSM-020): the Control Engineer risk-assesses first, and at 6.6 to 33 kV with customers off waits at least 5 minutes between 22:00 and 06:00, or 20 minutes between 06:00 and 22:00, for damage reports. SEF operation most likely means an overhead conductor on the ground. The event record reminds you of this whenever a fault leaves customers off.
- Fault level: OSM Section 2.4 (PR-NET-OSM-014) asks for the busbar fault level to be reduced before a reclose where it exceeds 150 MVA at 11 kV. Northgate is about 152 MVA at maximum with both transformers and the bus section in, just over that limit, so the event record reminds you to reduce it (opening the bus section brings it to about 82 MVA). Bramley is about 94 MVA, so no reduction is needed there.
Plant data and where it comes from
- Overhead lines: 50 mm² AAAC “Hazel” (7/3.30 mm) and 100 mm² AAAC “Oak” (7/4.65 mm), to BS 3242. Their impedances are calculated with Carson's equations for a typical 11 kV wood-pole flat formation and 100 Ωm earth, so you can check the method on the line card.
- Cables: 185 and 300 mm² aluminium XLPE, with sequence impedances from ENWL CP204.
- Distribution transformers: 11/0.433 kV ground-mounted units at 4.75 %, and pole-mounted units at 4.5–4.75 %.
- Primary transformers: 7.5/15 MVA (15 % on 15 MVA) and 11.5/23 MVA (27 % on 23 MVA), Dyn11 with an 11 kV NER. These sit inside the impedance envelope in Electricity North West's specification ES323 for 33/11 kV transformers, which is about 1 % per MVA of the emergency rating, with 23 to 27 % at nominal tap for a 23 MVA unit. ES323 also rules out solid earthing above 15 MVA.
- Typical PMCB settings: 240 A phase and 30 A earth fault are published mainline values from SP Energy Networks (SPEN's SEF is 20 A at 3 s; the jobs here use other SEF values so you have something to set). An SEF trip goes straight to lockout, with no reclose. Four trips to lockout, two instantaneous then two IDMT, with a 5 s dead time and 15 s reclaim, follow Electricity North West's published auto-reclose policy.
What it doesn't do
- Arc suppression coil (Petersen coil) earthing and its wattmetric or admittance earth-fault protection are not modelled. Both networks here are resistance-earthed.
- Distance protection, unit protection (pilot wire, differential) and transformer differential protection are not modelled. The jobs are about IDMT, fuse, recloser and sectionaliser grading on radial 11 kV networks.
- CT saturation uses a steady-state approximation: no DC offset or remanence. Inrush and cold load are checked against rules (12 times full load for 0.1 s; a load multiplier), not simulated as waveforms.
- Fuses and ASLs are treated as ganged three-phase devices. In reality each DOEF link and each ASL operates on its own phase, so an earth fault drops only the faulted phase and can leave a pole transformer single-phased.
- Fuse curves use the standard K and T melting points. Real links vary by manufacturer within those limits, so use the manufacturer's curve for a real setting study.
This is a training simulator. Real settings come from your company's protection policy and a proper study.